Working platforms and access scaffolding were used during the retrofitting of the GMA headquarters. The overall height to access was 51 meters.
- Compared to ordinary scaffolding, our clearance is higher: 2m per lift so better workability
- High elevation was the challenge but we provide easy access by using our Ringlock Aluminum Stairs
- High safety compliance
- We provide complete accessories
- Easy and faster to install. It takes approx. 3 days to complete 51m height installation
- Can adapt to the complexity of the structure, such as obstructions
- Total of 7 access towers of 51m
COFFRAL Products In Use
our solutions
COFFRAL Products In Use
More projects
Looking For A Rental Equipment Provider For Your Next Construction Project?
Subscribe To Our COFFRAL Newsletter
Looking for a rental equipment provider for your next construction project?
With More Than 50 Years Of Construction Experience
Subscribe To Our COFFRAL Newsletter
Previous
Next
CUSTOMIZED